Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
White Rock Road from Grant Line to Prairie City |
Description: This project will construct a high capacity, 4-lane roadway along the existing alignment of White Rock Road between Grant Line Road and Prairie City Road.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sacramento |
City | Rancho Cordova |
Zip Code | 95742 |
Senate District |
01 |
Assembly District | 10 |
Congressional District | 05 |
Caltrans District |
03 |
County/State Route | Sacramento 50 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 2679 | |
Lane Miles Added (Mixed) | 4.8 | |
Pavement Lane Miles | 2.74 | |
Peak Period Time Savings (minutes) | 181319 | 181319 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Sacramento County Dept of Transportation | Stephen White | 916-874-5354 | whitest@saccounty.net | |
Design (PS&E) Phase |
Sacramento County DOT | Stephen White | 916-874-5354 | whitest@saccounty.net | |
Right of Way Phase |
Sacramento County DOT | Stephen White | 916-874-5354 | whitest@saccounty.net | |
Construction Phase |
Sacramento County DOT | Stephen White | 916-874-5354 | whitest@saccounty.net | |
Corridor System Management Plan |
Caltrans | Jeff Pulverman | (916)274-0638 | jeff.pulverman@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$3,903 | $8,919 | $12,822 | ||||
Non-bond Funding | |||||||
Local** |
$5,000 | $-1,500 | $3,500 | ||||
Total**** | $8,903 | $7,419 | $16,322 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$900 | $543 | $1,443 | $1,435 | |||
Design(PS&E) |
$1,800 | $-550 | $1,250 | $1,250 | |||
Right of Way |
$5,201 | $-2,251 | $2,950 | $2,950 | |||
Construction |
$1,001 | $9,678 | $10,679 | $10,423 | |||
Total* | $8,903 | $7,419 | $16,322 | $16,058 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2007 07/01/2009 |
|
07/01/2007 07/01/2009 |
100 | 07/01/2007 07/01/2009 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2009 12/01/2010 |
|
07/01/2009 01/31/2012 |
100 | 07/01/2009 01/31/2012 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
07/01/2009 12/01/2010 |
|
07/01/2009 11/29/2011 |
100 | 07/01/2009 11/29/2011 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
05/01/2011 11/01/2012 |
|
04/30/2012 12/31/2013 |
100 | 04/30/2012 12/01/2013 |
0 1 |
|
Begin Closeout Phase
End Closeout Phase |
07/01/2009 06/01/2014 |
|
07/01/2009 06/01/2014 |
100 | 01/01/2014 06/01/2014 |
-55 0 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 04/01/2009 | 04/01/2009 | 100 | 05/01/2009 | -1 | ||
Implementation Date | 08/01/2008 | 08/01/2008 | 0 | 06/01/2009 | -10 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 2679 | |
Lane Miles Added (Mixed) | 4.8 | |
Pavement Lane Miles | 2.74 | |
Peak Period Time Savings (minutes) | 181319 | 181319 |
Bond Funding Cost | |
---|---|
Adopted: |
$3,903,000 |
Current Approved: |
$14,075,000 |
Actual Expenditures: |
$12,822,000 |
Status as of December 31, 2023.